March 24, 2008

Northstar Construction Update - March 24

Beginning later this spring, Northstar Construction Updates will begin including information on commuter rail station construction in Big Lake, Elk River, Anoka and Coon Rapids. This week, Northstar is continuing construction of the Light Rail Trainsit (LRT) connection in downtown Minneapolis and the Vehicle Maintenance Facility in Big Lake. Details on upcoming construction activities are included below.

Downtown Minneapolis - Light Rail Transit (LRT Connection)

  • Construction crews will continue decking work on the 5th Street North bridge over I-394.
  • Electric work beneath the 5th Street North bridge over the BNSF tracks continues.

City of Big Lake - Vehicle Maintenance Facility (VMF)

  • There are no anticipated traffic impacts related to VMF construction in the coming week.
  • Roofing work at the VMF has been completed.
  • Rail has been delivered to the VMF construction site. See photo below.

If you have any questions or concerns regarding Northstar construction or any other aspect of the Project, please contact Jonathan Blake at 651-366-5840 or by e-mail at jonathan.blake@mnrail.org. Please also visit Northstar online at www.mn-GetOnBoard.com.

For information on the new Minnesota Twins Ballpark, which is being constructed adjacent to Northstar's downtown Minneapolis construction site, visit the Minnesota Ballpark Authority (MBA) website at www.ballparkauthority.com or call 612-543-PARK. The MBA can provide you with information relating to construction of the Twins Ballpark and resulting traffic impacts.

Construction Site Photos

Hiawatha LRT ConnectionAtadecking_on_span_2_of_i394_brid_2

Decking work on 5th Street North bridge over I-394 (March 19, 2008)

Vehicle Maintenance FacilityView_of_stored_track_west_of_vm_b_2

Track stored west of the VMF (March 13, 2008)